Cost management as a part of integrated management of torrential watershed in Serbia: a case study of Topciderska River
Апстракт
This paper aimed to estimate the contingency reserves for the project related to the integrated management of Topciderska river in Serbia watershed, in the context of cost management, as a part of the risk analysis. The Monte Carlo simulation was used to determine the reserves. After the simulation, the distribution of probability for technical and biological works and distribution of probability of total costs was obtained. Cost contingency reserves are determined based on the difference between the costs specified by the project budget and the simulated total costs with 90% probability of occurrence. The cost reserve for the execution of the project amounted 19.45% of the total costs of estimated bill of quantities.
Извор:
Wasserwirtschaft, 2019, 109, 4, 33-38
DOI: 10.1007/s35147-019-0023-9
ISSN: 0043-0978
WoS: 000463251000005
Scopus: 2-s2.0-85086225656
Институција/група
Šumarski fakultetTY - JOUR AU - Baumgertel, Aleksandar AU - Dragović, Nada AU - Vulević, Tijana AU - Lukić, Sara PY - 2019 UR - https://omorika.sfb.bg.ac.rs/handle/123456789/1049 AB - This paper aimed to estimate the contingency reserves for the project related to the integrated management of Topciderska river in Serbia watershed, in the context of cost management, as a part of the risk analysis. The Monte Carlo simulation was used to determine the reserves. After the simulation, the distribution of probability for technical and biological works and distribution of probability of total costs was obtained. Cost contingency reserves are determined based on the difference between the costs specified by the project budget and the simulated total costs with 90% probability of occurrence. The cost reserve for the execution of the project amounted 19.45% of the total costs of estimated bill of quantities. T2 - Wasserwirtschaft T1 - Cost management as a part of integrated management of torrential watershed in Serbia: a case study of Topciderska River EP - 38 IS - 4 SP - 33 VL - 109 DO - 10.1007/s35147-019-0023-9 UR - conv_1402 ER -
@article{ author = "Baumgertel, Aleksandar and Dragović, Nada and Vulević, Tijana and Lukić, Sara", year = "2019", abstract = "This paper aimed to estimate the contingency reserves for the project related to the integrated management of Topciderska river in Serbia watershed, in the context of cost management, as a part of the risk analysis. The Monte Carlo simulation was used to determine the reserves. After the simulation, the distribution of probability for technical and biological works and distribution of probability of total costs was obtained. Cost contingency reserves are determined based on the difference between the costs specified by the project budget and the simulated total costs with 90% probability of occurrence. The cost reserve for the execution of the project amounted 19.45% of the total costs of estimated bill of quantities.", journal = "Wasserwirtschaft", title = "Cost management as a part of integrated management of torrential watershed in Serbia: a case study of Topciderska River", pages = "38-33", number = "4", volume = "109", doi = "10.1007/s35147-019-0023-9", url = "conv_1402" }
Baumgertel, A., Dragović, N., Vulević, T.,& Lukić, S.. (2019). Cost management as a part of integrated management of torrential watershed in Serbia: a case study of Topciderska River. in Wasserwirtschaft, 109(4), 33-38. https://doi.org/10.1007/s35147-019-0023-9 conv_1402
Baumgertel A, Dragović N, Vulević T, Lukić S. Cost management as a part of integrated management of torrential watershed in Serbia: a case study of Topciderska River. in Wasserwirtschaft. 2019;109(4):33-38. doi:10.1007/s35147-019-0023-9 conv_1402 .
Baumgertel, Aleksandar, Dragović, Nada, Vulević, Tijana, Lukić, Sara, "Cost management as a part of integrated management of torrential watershed in Serbia: a case study of Topciderska River" in Wasserwirtschaft, 109, no. 4 (2019):33-38, https://doi.org/10.1007/s35147-019-0023-9 ., conv_1402 .